Thursday, May 17, 2012
Tuesday, April 17, 2012

Downtown Street Projects - Weekly Updates from Chuck Stearns: April 17, 2012
2ND Street Reconstruction – TIGER Grant
Work continues on the intersection of 2nd and Spokane. Good news was that the road base material below the intersection was good material, so they did not have to export bad material and import new structural fill material. This circumstance saved about a week of time for hauling material in and out and compacting the new material.
Compaction is mostly complete and the SW corner of 2nd and Spokane has a new, wider turning radius.
Given that this phase of the project has a lot more concrete than other phases, the rainy weather is starting to hamper concrete pours. Right now they are still holding to a project completion in late May.
Pouring concrete sidewalk on 2nd Street on 4-17
THIS WEEK’S WORK
Pouring of sidewalks on 2nd Street and in front of the Downtowner Inn on Spokane will continue. Finishing the pouring of concrete curbs and gutters will also continue. The placement of traffic signal poles and street lights as shown below will also continue.
NEXT WEEK (APRIL 23-27)
The pouring of concrete will continue as will the placing of the traffic signal poles and street lights. The landscaping sub-contractor is scheduled to arrive on April 23rd to start planting street trees and landscaping.
Friday, March 30, 2012
April, 2012 - Construction at 2nd and Spokane to resume
Monday, October 24, 2011

Downtown Street Projects - Weekly Updates from Chuck Stearns: October 24, 2011
OPEN !
CENTRAL AVENUE PROJECT
As the picture below shows, the Central Avenue project between 1st Street and Railway opened up on Saturday, October 22nd. While there are still some clean-up and probably some punch list items, this project completes the three year Downtown Street Improvements projects – this project was the sixth and last phase. Thanks to all citizens and affected businesses for their patience and support.
2ND Street Reconstruction – TIGER Grant
The Hwy93 – 2nd Street project also began paving on Monday, October 24th as the pictures below show. In addition to paving this week, the concrete work will continue with the installation of concrete crosswalks in the Central Avenue intersection followed by alley aprons and then sidewalks next to all of the buildings.
The contractor LHC will not likely open up 2nd Street until all or most of the concrete work is done as it is safest and most efficient for them to have the entire working area. Central Avenue through 2nd Street may re-open later this week however.
The entire project for this fall phase will likely shut down and 2nd Street will re-open sometime in early to mid-November.
Friday, October 14, 2011

Downtown Street Projects - Weekly Updates
from Chuck Stearns: October 14, 2011
WHOLE LOTTA SHAKIN’ GOIN’ ON – HOME STRETCH
2ND Street Reconstruction – TIGER Grant
The good news is that digging, muddin’ around in the muck, and the water and storm drain pipe work is rapidly coming to an end. The recent rains had a great impact while the clay sub-surface was exposed. Most of the clay muck is on the way out and the new structural fill is being put in and compacted. That compaction means that there are a lot of vibrations going on in this project and in the Central Avenue project. However compaction gets followed by installation of concrete and installation of concrete gets followed by asphalt pavement, so we are in the home stretch of the fall projects.
The pictures below show 2nd Street in front of City Hall getting rolled and tested for compaction. The contractor still hopes to pave during the week of October 24th.
Central Avenue Project
Central Avenue continues with the pouring of concrete and finish grading of the road. The contractor hopes to pave on Thursday, October 20th and open the road on or before October 22nd.
Thursday, October 6, 2011

Downtown Street Projects - Weekly Updates from Chuck Stearns: October 6, 2011
Traffic signals and lanes
Many people may wonder why the turn lanes on Baker Avenue at the 2nd Street intersection are blocked. It is because the large semi-trucks which are turning at that intersection need a wide path in order to make the 90° turn. Therefore it is safest during the month of October to leave those lanes closed. Also, the traffic signal controller device is still the old controller and the new controller will not arrive until next spring. However, all lanes should be open when the entire project is opened for the winter in November.
2ND Street Reconstruction – TIGER Grant
The Baker Avenue and 2nd Street intersection was opened on Monday, October 3rd and the detour route was modified so that all detours are on Baker Avenue. Baker Avenue experienced some congestion this week, especially for northbound vehicles turning left onto 2nd Street – Hwy 93. Even though the traffic signal controller is the former controller because the new controller will not arrive until next spring, we were able to lengthen the green light signal for north and south on Baker Avenue, so that should help alleviate congestion during October. The entire project will re-open for the winter months in November, 2011 through March, 2012 and then construction will resume next April – June.
As the picture below shows, the “big dig” arrived at the Central Avenue intersection this week as the water main and storm drain installation continued to move eastward. The alley between Spokane and Central Avenue should re-open today, but it will have sporadic closures next week.
Central Avenue Project
The pouring of concrete for street light stands and curbs and gutters began this week. The pouring of sidewalks will likely occur early next week. The contractor may try to pave the road on October 17-19. The contractor is still ahead of schedule and should finish before October 22nd.













